Mid-Valley Hospital Water Service Improvement Project

The Hospital water supply is currently provided by a single water service line which is on a dead end mainline partially constructed of AC pipe. The bypass meter has failed so there is now no way to do service work on the water meter without shutting off the water supply to the hospital.
    This project will connect a new primary service line and meter to the existing Main water pipe east of the hospital. It will allow a bypass so work can be done on the Meter without disrupting service to the Hospital.

Projected Timeline-

Week of March 24th

Traffic Control Set up,  Exploratory Excavation, Insertion of New Valve 

Week of April 7th-

Excavation for new vault, Set Water Vault and back fill, Build and test Water Vault Piping

Week of April 14th

Pour Curb and Gutter, Prep and Pave Parking lot and Roadway, Site restoration