Projected Timeline

Week of March 17th

Site Work- Mobilization, TESP, Demolition, Cleanup, Rough grading, Underground piping, Underground electrical

Week of March 24th

Site Work- Roll off slab

Building- Excavate Footings, Pour building footings and slab, 

Week of April 7th

Site Work- Sewer

Resevoir- Reservoir pad, and Resevoir

Week of April 21st

Building- Walls

Week of May 5th

Building- Inside Piping

Week of May 19th

Site Work- Gravel Site

Building- Roofing

Week of May 26th

Building- Building electrical

Week of June 9th

Building- Paint

Week of June 14th

Building- Pipe Labels

Week of July 21st

Site- Set generator, Bollards concrete floor, System setting and start-up

Week of July 28th

Fencing