Central Avenue Project

Google map of Central Ave Project in Omak WA

Central Ave Project

The Central Ave Project will replace sewer lines and repair or replace Storm Drain lines in the area highlighted. There will be some street work as well as some additional sidewalk areas. We will also be replacing sewer connection lines to homes with older lateral lines. The work is scheduled for the Summer of 2025. We will update with a timeline when the Contractor is selected. 

 

Construction Timeline

Construction Starts July 9th 2025

 

Week 1

Survey manholes, catch basins and pipe offset

Remove all storm and storm pipe

Cut and finish removing concrete

Pot hole for utility conflict

Unload piping material

 

Week 2

Start pot holing side services at houses on fir street

Clean and camera all sewer main

Fuse bypass pipe together for doing storm Cb 1 and work associated

Receive manholes and catch basins 

 

Week 3

Mainline sewer work on Fir street

Burst side services Fir street

Setup storm bypass for 18 inch storm line at CB 1